News
AI Summary
1 Jul 202616 Muharram 1448 AH
AI Computing Demand Is Pushing Global Power Grids to the Breaking Point

AI Computing Demand Is Pushing Global Power Grids to the Breaking Point

Gartner's report reveals that global data center energy consumption will reach 565 terawatt-hours by 2026, marking a 26% annual increase. This figure is projected to exceed 1,200 terawatt-hours by 2030, surpassing Japan's total annual consumption. In the same week, 75 data center projects in the U.S., valued at $130 billion, were postponed or canceled due to energy shortages. Satya Nadella, CEO of Microsoft, expressed concerns about the energy distribution capacity in relation to data facilities.